Setbacks are the minimum distances between parts of a septic system and the things they could harm or be harmed by: drinking water wells, surface water, water lines, buildings and neighbors. In Georgia they are set in Chapter 511-3-1 of the Department of Public Health's rules, and the county board of health applies them during permitting. Hall County's application requirements ask for a to-scale site plan that shows the house, driveway, decks, the primary and reserve septic areas, and any creek, pond, lake, springhead or well with the required setbacks.
Setbacks also limit later projects. A pool, garage, driveway or addition that crowds the tank or field can be refused, which is one reason Hall County asks building permit applicants on septic to contact Environmental Health first.
Septic tank setbacks
Georgia's rules say no septic tank may be installed less than fifty feet from existing or proposed wells, springs, sinkholes or suction water lines, and tanks should be downgrade from wells or springs where physically possible. Tanks may not be less than twenty-five feet from geothermal boreholes, lakes, ponds, streams, water courses and other impoundments, less than ten feet from pressure water supply lines, or less than ten feet from a property line. No tank may be less than fifteen feet from a drainage ditch or embankment.
The rules add that tanks should be installed for ready maintenance access and should be at least ten feet from hardscape, drives, swimming pools and building foundations. The county board of health may allow lesser distances or require greater ones after a site inspection, because of topography, lot shape, soil or groundwater.
| Feature | Septic tank minimum | Absorption field minimum |
|---|---|---|
| Wells, springs, sinkholes | 50 ft | 100 ft |
| Suction water lines | 50 ft | 10 ft (water supply lines) |
| Pressure water supply lines | 10 ft | 10 ft (water supply lines) |
| Lakes, ponds, streams, impoundments | 25 ft | 50 ft from normal water level |
| Geothermal boreholes | 25 ft | 50 ft |
| Property lines | 10 ft | 5 ft |
| Drainage ditch or embankment | 15 ft | 15 ft |
| Buildings with basements | 10 ft recommended (foundations) | 10 ft |
| Buildings without basements, structures, drives, hardscape | 10 ft recommended | 5 ft |
| Swimming pool | 10 ft recommended | 15 ft (pool foundation) |
Absorption field setbacks
The drain field's distances are stricter where water supplies are involved. No absorption field may be built less than one hundred feet from existing or proposed wells, springs or sinkholes; less than ten feet from water supply lines and buildings with basements; or less than five feet from buildings without basements, other structures, drives, hardscape and property lines. Fields must be at least fifteen feet from an embankment, swimming pool foundation, drainage ditch or trash pit, and at least fifty feet from geothermal boreholes and the normal water level of any impoundment, tributary, stream or other body of water, including ponded wetlands.
If a water supply line crosses or comes within ten feet of the field, Georgia requires it to run at least twelve inches above the top of the absorption line's aggregate layer and to be encased in a single length of larger pipe. The rules also bar fields where groundwater, soil or geology would interfere with treatment.
Want a provider to look at your system?
Free Quote RequestWhat this means near Lake Lanier and Hall County creeks
Many Hall County lots front Lake Lanier, a tributary or a farm pond. The fifty-foot field setback and the twenty-five-foot tank setback from surface water are measured from the normal water level, so shoreline lots often have less usable area than their acreage suggests. That is where a soil report and an early conversation with Environmental Health save money.
On tight sites, an engineered system may fit where a conventional field will not; see advanced treatment and pump systems. If you are repairing an old field near water, read drain field repair, because a repaired field must meet current rules.
Using setbacks when you plan a project
Before you design a pool, patio or addition, get the county septic record so you know where the tank, field and reserve area are; our tank locating guide explains how. Then measure from each feature to the distances above, and expect the county to check them.
If the numbers do not work, the options are moving the project, relocating part of the system with a permit, or a different system type. For permits, see Hall County septic permit guide.
Reading the distances correctly
Setbacks are minimums, not targets. Georgia's rules let the county board of health require greater distances where topography, lot shape, soil or groundwater call for them, as well as allow lesser ones in some cases after a site inspection. Treat the numbers in the table as the floor and expect the county to apply them to your specific lot.
Some distances depend on the feature's type. A building with a basement needs ten feet from a field; one without needs five. A suction water line needs fifty feet from a tank; a pressure line needs ten. Wells and springs carry the largest distances because they are drinking water sources.
Measure from the right points. The surface-water setbacks for fields are measured from the normal water level of an impoundment or stream. When in doubt, ask Hall County Environmental Health before you finalize a site plan.